USH 51/N. Star Road Intersection Project Profile

Merrill to Tomahawk, WisDOT ID 1176-24-70

Client

  • WisDOT NC Region

Dates

  • Construction 2013

Estimated Construction Cost

  • $1.8M

Merrill to Tomahawk, WisDOT ID 1176-24-70

This project built a two-span grade separation structure over USH 51 to eliminate an at-grade intersection. Lane shifts and lane closures were required on USH 51 to accommodate equipment while building the pier and abutments. USH 51 was detoured on CTH K for two consecutive evenings to facilitate the erection of the precast concrete beams. The traffic control was managed in conjunction with a separate pavement rehabilitation project on USH 51. The project had an expedited timeframe and required coordination of nine subcontractors.

Key Elements

  • Bridge construction
  • HMA pavement
  • Wetlands
  • Grading
  • Expedited timeframe
  • Extensive subcontractor coordination